The contract T3 of the new Line C of the Rome underground is 2.8 km long and includes two stations and two ventilation shafts. It runs under the archaeological artefacts of the historical centre of Rome which is a UNESCO World Heritage site, an area with high density of monuments and historical buildings. Metro C, in cooperation with an interdisciplinary Scientific Technical Committee, has carried out several detailed studies to analyse the potential interactions of the monuments/historical buildings with the new line C, in order to identify the most appropriate and effective mitigation techniques to be adopted to prevent any damage. This paper describes the procedures that have been followed to safeguard the monuments/historical building interacting with the line during its construction, from the approach adopted to study the line-monument interaction at different levels of complexity, to the comparison between the computed and the observed displacement fields for the case of the Basilica di Massenzio.

Tunnelling effects on the Basilica di Massenzio: Computed and observed displacement fields / Romani, E.; D’Angelo, M.; Sidera, L.; Sciotti, A.; Ottaviani, C.; Rampello, S.. - 1:(2022), pp. 1043-1056. (Intervento presentato al convegno THIRD INTERNATIONAL ISSMGE TC301 SYMPOSIUM, NAPOLI, ITALY, 22–24 JUNE 2022 tenutosi a Napoli) [10.1201/9781003308867-82].

Tunnelling effects on the Basilica di Massenzio: Computed and observed displacement fields

S. Rampello
Writing – Original Draft Preparation
2022

Abstract

The contract T3 of the new Line C of the Rome underground is 2.8 km long and includes two stations and two ventilation shafts. It runs under the archaeological artefacts of the historical centre of Rome which is a UNESCO World Heritage site, an area with high density of monuments and historical buildings. Metro C, in cooperation with an interdisciplinary Scientific Technical Committee, has carried out several detailed studies to analyse the potential interactions of the monuments/historical buildings with the new line C, in order to identify the most appropriate and effective mitigation techniques to be adopted to prevent any damage. This paper describes the procedures that have been followed to safeguard the monuments/historical building interacting with the line during its construction, from the approach adopted to study the line-monument interaction at different levels of complexity, to the comparison between the computed and the observed displacement fields for the case of the Basilica di Massenzio.
2022
THIRD INTERNATIONAL ISSMGE TC301 SYMPOSIUM, NAPOLI, ITALY, 22–24 JUNE 2022
tunnelling, soil-structure interaction, historical monuments, monitoring, numerical analyses
04 Pubblicazione in atti di convegno::04b Atto di convegno in volume
Tunnelling effects on the Basilica di Massenzio: Computed and observed displacement fields / Romani, E.; D’Angelo, M.; Sidera, L.; Sciotti, A.; Ottaviani, C.; Rampello, S.. - 1:(2022), pp. 1043-1056. (Intervento presentato al convegno THIRD INTERNATIONAL ISSMGE TC301 SYMPOSIUM, NAPOLI, ITALY, 22–24 JUNE 2022 tenutosi a Napoli) [10.1201/9781003308867-82].
File allegati a questo prodotto
File Dimensione Formato  
Tunnelling_Romani_2022.pdf

accesso aperto

Tipologia: Versione editoriale (versione pubblicata con il layout dell'editore)
Licenza: Creative commons
Dimensione 1.79 MB
Formato Adobe PDF
1.79 MB Adobe PDF

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/11573/1640231
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus ND
  • ???jsp.display-item.citation.isi??? ND
social impact