Operation of long EHVAC cable interconnectors requires controlling voltage/reactive power profiles. With reference to a hypothetical 200 km long 400 kV-50 Hz cable system, connecting to the grid three large OWFs with 2 GW total capacity, the paper compares results yielded by a dedicated algorithm with those of a standard OPF software. A parametric study of the interconnector was carried out, considering different dispatch scenarios and boundary conditions (network connection point voltages). Several cases were ran for an enlarged, meshed test system including the interconnector. Results show that solutions yielded by OPF and by the authors' algorithm are very close, confirming the effectiveness of the latter but also its possible replacement by a standard OPF when dealing with non-radial cable system topologies.
Optimal power flow application to EHVAC interconnections for GW-sized Offshore Wind Farms / Lauria, Stefano; Maccioni, Marco; Schembari, M.; Codino, Asia; Faza, A.. - (2016), pp. 1-6. (Intervento presentato al convegno 16th International Conference on Environment and Electrical Engineering, EEEIC 2016 tenutosi a Firenze (ITA) nel 2016) [10.1109/EEEIC.2016.7555650].
Optimal power flow application to EHVAC interconnections for GW-sized Offshore Wind Farms
LAURIA, Stefano;MACCIONI, Marco;CODINO, ASIA;
2016
Abstract
Operation of long EHVAC cable interconnectors requires controlling voltage/reactive power profiles. With reference to a hypothetical 200 km long 400 kV-50 Hz cable system, connecting to the grid three large OWFs with 2 GW total capacity, the paper compares results yielded by a dedicated algorithm with those of a standard OPF software. A parametric study of the interconnector was carried out, considering different dispatch scenarios and boundary conditions (network connection point voltages). Several cases were ran for an enlarged, meshed test system including the interconnector. Results show that solutions yielded by OPF and by the authors' algorithm are very close, confirming the effectiveness of the latter but also its possible replacement by a standard OPF when dealing with non-radial cable system topologies.File | Dimensione | Formato | |
---|---|---|---|
Lauria_Optimal_2016.pdf
solo gestori archivio
Tipologia:
Versione editoriale (versione pubblicata con il layout dell'editore)
Licenza:
Tutti i diritti riservati (All rights reserved)
Dimensione
377.8 kB
Formato
Adobe PDF
|
377.8 kB | Adobe PDF | Contatta l'autore |
I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.