Meshed HV subtransmission networks are subject to undesirable parallel (unscheduled) active power flows from the EHV system. The phenomenon is worsened by conversion of HV overhead lines to underground cables (UGCs), which increases parallel flows through the HV network because of the attendant reduction in HV line reactance; the effect increase with network extension and are compounded by UGC charging power. The study deals with the assessment of the maximum undergrounding degree for a given subtransmission network. An analytical formulation of maximum HV line extension length as a function of EHV power flow and undergrounding degree is given; optimum UGC shunt compensation requirements are evaluated. Application to a typical 150 kV–50 Hz network is presented, showing a very good agreement with power flow simulation. In particular, the case study evidences that complete undergrounding of the HV network is possible if line length is under 50 km; the proposed shunt compensation effectively raises this limit to 70 km.

Maximum undergrounding degree of HV subtransmission networks as dictated by unscheduled power flows / Lauria, Stefano; Palone, Francesco. - In: IET GENERATION, TRANSMISSION & DISTRIBUTION. - ISSN 1751-8687. - 7:11(2013), pp. 1202-1209. [10.1049/iet-gtd.2012.0295]

Maximum undergrounding degree of HV subtransmission networks as dictated by unscheduled power flows

LAURIA, Stefano;PALONE, FRANCESCO
2013

Abstract

Meshed HV subtransmission networks are subject to undesirable parallel (unscheduled) active power flows from the EHV system. The phenomenon is worsened by conversion of HV overhead lines to underground cables (UGCs), which increases parallel flows through the HV network because of the attendant reduction in HV line reactance; the effect increase with network extension and are compounded by UGC charging power. The study deals with the assessment of the maximum undergrounding degree for a given subtransmission network. An analytical formulation of maximum HV line extension length as a function of EHV power flow and undergrounding degree is given; optimum UGC shunt compensation requirements are evaluated. Application to a typical 150 kV–50 Hz network is presented, showing a very good agreement with power flow simulation. In particular, the case study evidences that complete undergrounding of the HV network is possible if line length is under 50 km; the proposed shunt compensation effectively raises this limit to 70 km.
2013
electric reactance; load flow; power overhead lines; transmission networks; underground cables
01 Pubblicazione su rivista::01a Articolo in rivista
Maximum undergrounding degree of HV subtransmission networks as dictated by unscheduled power flows / Lauria, Stefano; Palone, Francesco. - In: IET GENERATION, TRANSMISSION & DISTRIBUTION. - ISSN 1751-8687. - 7:11(2013), pp. 1202-1209. [10.1049/iet-gtd.2012.0295]
File allegati a questo prodotto
Non ci sono file associati a questo prodotto.

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/11573/530752
 Attenzione

Attenzione! I dati visualizzati non sono stati sottoposti a validazione da parte dell'ateneo

Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus 5
  • ???jsp.display-item.citation.isi??? 4
social impact