This paper presents a strategy to avoid peak demand rising and energy management due to existing cranes at container terminals (CT). The new generation of the Ship to Shore (STS) cranes installed at the port of Long Beach (POLB) are equipped with the capabilities to absorb up to 90% of the regenerative energy (RE). Hence, a percent of RE is fed into the dc-bus in an STS Crane and deliver to the Ultracapacitor (UC) bank energy storage system (ESS). As an effective method, UC sizing is able to do the local peak shaving in each STS Crane and then with the remaining percent of the RE by the duty cycle coordination for the STS group Cranes the overall peak power minimization in point of delivery has been reviewed based on PSO algorithm. Results in MATLAB shows the two proposed methods can reduce the peak power demand and increase the percentage of the utilization energy factor (UEF) in STS cranes.

Utilization of Regenerative Energy by Ultracapacitor Sizing for Peak Shaving in STS Crane / Kermani, M.; Parise, G.; Martirano, L.; Parise, L.; Chavdarian, B.. - (2019), pp. 1-5. (Intervento presentato al convegno 19th IEEE International Conference on Environment and Electrical Engineering and 2019 IEEE Industrial and Commercial Power Systems Europe, EEEIC/I and CPS Europe 2019 tenutosi a Genoa, Italy) [10.1109/EEEIC.2019.8783770].

Utilization of Regenerative Energy by Ultracapacitor Sizing for Peak Shaving in STS Crane

Kermani M.;Parise G.;Martirano L.;Parise L.;
2019

Abstract

This paper presents a strategy to avoid peak demand rising and energy management due to existing cranes at container terminals (CT). The new generation of the Ship to Shore (STS) cranes installed at the port of Long Beach (POLB) are equipped with the capabilities to absorb up to 90% of the regenerative energy (RE). Hence, a percent of RE is fed into the dc-bus in an STS Crane and deliver to the Ultracapacitor (UC) bank energy storage system (ESS). As an effective method, UC sizing is able to do the local peak shaving in each STS Crane and then with the remaining percent of the RE by the duty cycle coordination for the STS group Cranes the overall peak power minimization in point of delivery has been reviewed based on PSO algorithm. Results in MATLAB shows the two proposed methods can reduce the peak power demand and increase the percentage of the utilization energy factor (UEF) in STS cranes.
2019
19th IEEE International Conference on Environment and Electrical Engineering and 2019 IEEE Industrial and Commercial Power Systems Europe, EEEIC/I and CPS Europe 2019
peak shaving; PSO; regenerative energy (RE); ship to sore crane; ultracapacitor
04 Pubblicazione in atti di convegno::04b Atto di convegno in volume
Utilization of Regenerative Energy by Ultracapacitor Sizing for Peak Shaving in STS Crane / Kermani, M.; Parise, G.; Martirano, L.; Parise, L.; Chavdarian, B.. - (2019), pp. 1-5. (Intervento presentato al convegno 19th IEEE International Conference on Environment and Electrical Engineering and 2019 IEEE Industrial and Commercial Power Systems Europe, EEEIC/I and CPS Europe 2019 tenutosi a Genoa, Italy) [10.1109/EEEIC.2019.8783770].
File allegati a questo prodotto
File Dimensione Formato  
Kermani_Utilization_2019.pdf

solo gestori archivio

Tipologia: Versione editoriale (versione pubblicata con il layout dell'editore)
Licenza: Tutti i diritti riservati (All rights reserved)
Dimensione 504.18 kB
Formato Adobe PDF
504.18 kB Adobe PDF   Contatta l'autore

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/11573/1322126
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus 13
  • ???jsp.display-item.citation.isi??? 4
social impact